This morning’s task was to build the conduit racks that will locate all of our conduits in the proper position for their associated panels, transformers and other gear. It’s a tedious job and takes quite a bit of time to get these set up in the correct position and stable enough to ensure nothing moves when you are working on it or when concrete is poured.
As the night sky faded, we had 2 of the 4 racks completed.
By 7 AM we had three of the four conduit racks completed and ready to go. The fourth one will have to wait till next week as it was time for us to load up clean up the job site and roll our hoop for Home.
Originally posted on: August 22, 2025 at 3:28 pm